An AEC firm runs on a document set that keeps changing. This guide shows which RFI, submittal, spec and closeout work AI can draft, what stays with a licensed professional, and how little has been measured so far.

Why the document set is the place to start

Every project runs on a set of documents that is never finished. Addenda change the bid set. Bulletins and supplemental instructions change the issued set. The answer to a field question may sit in a spec section, an approved submittal, an RFI from four months ago or an email nobody filed.

So a good part of the week goes to working out what is current and where it says so. A much-quoted measure comes from a 2018 survey of 599 construction leaders by FMI and PlanGrid, a software vendor now owned by Autodesk. Respondents estimated that team members spend more than 14 hours a week on conflict, rework and similar issues, including about five and a half hours hunting for project data, and they attributed 48% of rework to miscommunication and poor project data.[1]

Those are eight-year-old self-estimates from people who were asked, with no measurement on actual jobs. Use them for a sense of scale and no more. If you see $177 billion quoted as the cost of rework, that misreads the same release: the $177.5 billion is a modeled labor cost for all non-optimal time, built from those survey estimates.[1]

RFIs show the pattern most clearly

A request for information, or RFI, is a formal question about the contract documents. One large dataset is a 2013 Navigant Construction Forum study of 1,083,807 RFIs on 1,362 projects, which found an average of 796 per project and a median reply time of 9.7 days.[2] Read the sample before borrowing those numbers. The data came from Aconex, a vendor platform. Each project had at least 100 RFIs, 79% of the projects were in Australia and New Zealand, and the work ran from 2001 to 2012.[2] The same study estimated $1,080 and 8 hours to review and answer one RFI, using assumed hours and rates, so treat that as one older estimate rather than a current U.S. cost.[2]

One detail in that study matters more for AI than the headline. It cites a Wisconsin DOT highway study in which 13.2% of RFIs were not justifiable, a group that includes questions already answered in the contract documents.[2] That is one highway study, reported second-hand. It still names the cheapest RFI to deal with: the one that a good search would have closed before it left the jobsite.

The people doing this reading are scarce

In the 2025 workforce survey from the Associated General Contractors of America (AGC), 45% of firms reported project delays from worker shortages.[3] Among firms seeking them, 77% listed estimating staff as hard to fill and 76% said the same of project managers and supervisors.[3] AGC is a trade group and those answers came from its members, but the point will be familiar: the people who read documents all day are the people you can least spare.

None of these figures is an AI result. They describe the size of the problem. How much AI shrinks it has barely been measured, and we come back to that below.

Who does what, from bid to closeout

Most AEC work sorts cleanly once you ask one question about each step: does this read and draft, does it follow a fixed rule, or does someone’s license, contract or money stand behind it?

A project’s paperwork, sorted by who should do it

  1. Bid documents

    • Read specs and general conditions
    • List risk clauses and scope questions
    • Draft proposal sections
    AI
  2. Pursue and price

    • Decide whether to pursue
    • Set the fee or bid
    • Accept contract risk
    Person
  3. Submittal log

    • Pull required items from each spec section
    • Propose trade and reviewer
    • Show the source paragraph
    AI
  4. Tracking and routing

    • Due dates and ball-in-court reminders
    • Route by discipline
    • Log each status change
    Rule
  5. First pass on RFIs and submittals

    • Search documents and past RFIs
    • Flag duplicates
    • Draft replies and comments with citations
    AI
  6. Design and code judgment

    • Answer design questions
    • Stamp submittals
    • Decide if a reply changes scope, cost or time
    Person
  7. Daily records

    • Draft daily reports from notes
    • Draft meeting minutes
    • Answer “where is the latest?”
    AI
  8. Closeout

    • Checklist of O&Ms, warranties and as-builts by spec section
    • Chase missing items on schedule
    • Package for a person’s sign-off
    Rule
Our mapping of a typical project. It shows a sensible division of work, not what firms have adopted.

Notice where the line falls. AI sits on the reading side of each document. People sit at the moment a document leaves the firm or binds it. The grey stages are not AI at all: a due date and a routing table do not need a language model, and using one there adds cost and risk for nothing. Our guide to AI, automation and RPA covers that choice.

The technique behind most of the blue stages is called retrieval-augmented generation, or RAG. The system first searches your documents, then writes only from the passages it found, and cites them. Our RAG guide explains how it is built. For a project team, the citation is what matters: it turns a draft from something you have to trust into something you can check in a minute.

RFIs: screen first, draft second

The obvious pitch is drafting the answer. We would lead with the screen, because it is lower risk and it can reduce the volume of work as well as its speed. A sensible first pass runs like this.

  1. Read the RFI and pull out its subject, discipline, and any sheet or spec references.
  2. Search the current contract documents, approved submittals and earlier RFIs on the job.
  3. Sort it into one of three groups: already answered in the documents, a duplicate of an earlier RFI, or a real question.
  4. For a real question, draft a reply that cites document, sheet and revision.
  5. Route it to a named reviewer. If the draft touches scope, cost or schedule, flag that so it moves through your change process and not as a casual reply.

Which side of the RFI you sit on changes the value. A general contractor or trade partner gains most from the screen: weak questions get closed in-house, and the ones that do go out are better framed, with the conflict shown and the references attached. An architect or engineer gains most from consistency: the same detail answered the same way across consultants, and the RFI your team has answered three times this year recognized as such.

One RFI, before and after

Today

  1. RFI arrives in email or the project system
  2. Project manager forwards it to the architect or engineer
  3. Reviewer searches drawings, specs and old RFIs
  4. Someone confirms which revision is current
  5. Reply is written from memory and whatever was found
  6. Nobody records that the question came up before

The reply waits for whoever has time to search.

With a cited first pass

  1. RFI is read and logged
  2. AI searches the current set and past RFIs
  3. Duplicates and answered questions are flagged
  4. A draft arrives with sheet, section and revision cited
  5. A named reviewer opens each citation and edits
  6. Reviewer sends it, and scope or cost items go to change management

Searching shrinks. The judgment and the signature do not move.

An illustrative sequence. We have no reliable measure of how much time this saves at a small or midsize firm.

What AI cannot do here is as important. It cannot resolve a true conflict between drawing and spec, because that is a design decision. It cannot see the jobsite. And it cannot tell you what the design team intended where the documents are silent, though it will sometimes write as if it can. A well-built system should say “not found in the documents” rather than fill the gap, and you should test that behavior deliberately.

Submittals: the log is easy, the stamp is not

A submittal log is a list hidden in a long document. Each specification section spells out what the trade must submit: product data, shop drawings, samples, test reports, closeout items. Building the log means reading every section and copying those items out, and then doing it again when an addendum lands.

This suits AI well. The input is long, the task is reading, and each entry can point back to its source paragraph so a person can spot-check it. The failure mode is a missed item, so review the log against a sample of sections by hand and do not assume it is complete.

Comparing product data with the spec

The harder task is checking a cut sheet against the spec: rating, finish, voltage, listing, named manufacturers, “or approved equal” language. AI can line up the requirement beside the product data and draft review comments for the engineer or architect. This is promising, and it is also where we would be most careful, for three reasons.

  • Cut sheets often show a family of products, and the marked option may be a circle on a scan.
  • Requirements can live on the drawings, in schedules or in general notes, away from the section being checked.
  • A substitution dressed as a compliant product is exactly the case a reviewer is there to catch.

We found no production accuracy figures for AI spec or submittal review that we could rely on. So build your own: take a batch of past submittals with known outcomes, including ones you rejected, and see whether the tool finds what your reviewer found. Approved, approved as noted, revise and resubmit: those stamps remain a person’s call.

Specs and project records: one answer, with its source

The everyday question on most projects is plain: where is the latest version, and what did we agree? AI can help with a few kinds of this work.

  • Spec work. Summarizing long sections, comparing versions, and pulling requirements into checklists for QA. Comparing a section with the last project’s version can also expose leftovers from a master spec.
  • Project questions. Answering “where is the latest” across email, drawings and logs, for people in the office or the field.
  • Daily records. Drafting daily reports and meeting minutes from notes, for the superintendent or project manager to correct.
  • Closeout. Assembling O&M manuals, warranties and as-builts against the spec’s list of what is owed.
  • Preconstruction. Reading bid documents, drafting proposals and listing risky contract clauses for a person to weigh.

Document control is also where the gap between interest and use shows up. In a Dodge survey with CMiC, a vendor that sells AI software, 37% of contractors were aware of AI for document access and version control and 8% used it.[4] Those values were read from a chart, and the sample is 235 firms.

Do you need clean data first?

Not across twenty years of archives. In the same survey only 26% of contractors rated their current data quality as high, so if you waited for perfect data you would wait a long time.[4] What you do need, for one project, is narrower: a defined current set, revisions that can be told apart, superseded documents marked as superseded, and permissions that reflect who may see what. Change orders and fee records should not surface for everyone who asks a question.

What the adoption numbers do and do not tell you

You will see AEC adoption quoted anywhere from single digits to more than half. Those figures are not really in conflict, because they count different things.

Four surveys, four different questions

SourceFindingHow to read it
Dodge with CMiC, 235 U.S. contractors, fall 2025On average 32% are aware of each AI project-management function and 5% use each.[4]Vendor partner. “Small” here means $25M to $49M in revenue.[4]
AIA with Deltek and ConstructConnect, March 20256% of architectural professionals regularly use AI. 8% of firms had implemented it, and 20% more were working on it.[5]Sample not stated on the page. Adoption was driven by firms of 50 or more employees.[5]
Deltek Clarity study, reported May 202553% of A&E firms use AI tools, up from 38%.[6]Vendor study, read second-hand. “Any use” counts, which is why it runs so far above AIA’s figure.
AGC members, summer 202545% expect AI and robotics to help by automating manual, error-prone tasks, and 12% expect job losses.[3]Opinion about the future, with no results behind it.

Occasional use of a chatbot can count toward the high figures. The low ones ask about regular use or a finished implementation. All of these are also dated in a market moving this quickly.

The worries are more informative than the adoption rates. In the Dodge survey, 57% of contractors worried about the accuracy of AI output and 54% about the security of company data, and cost concerned 49% of small and midsize contractors against 26% of large ones.[4] Those are reasonable worries. The first two are what the rest of this article tries to answer.

What we could not find measured

We looked for reliable figures on these questions and found none:

  • Time saved per RFI or submittal with AI at a small or midsize U.S. firm.
  • Reduction in rework from AI.
  • Accuracy of AI spec or submittal review in production use.
  • AI use by task at firms under $25M in revenue, which the Dodge survey does not reach.[4]

So we will not give you a savings figure, and you should press anyone who does on who was measured and how. A saving reported by a vendor’s large enterprise customers says little about a 30-person engineering office.

Licensure, liability and project confidentiality

This section describes rules and practice as of November 2026. It is not legal advice, and the professional bodies are still working out the details.

Responsible control does not move

NCARB, the national architectural licensing council, has said AI is a tool and no replacement for professional judgment, and that the licensed practitioner must remain in responsible control. It also said it would examine further how responsible control applies to AI.[7] That report dates from November 2024, so check for updates with your state board.

On the engineering side, an NSPE position statement calls for verification, validation and monitoring of AI systems that affect public safety. The copy we read was adopted in September 2023. A 2025 revision has been reported, and we could not confirm it.[8]

In practice, responsible control means the review has to be real. A reviewer who skims a stack of tidy drafts without opening the cited sheets is not reviewing them, and well-written output makes that lapse more likely. Our guide to human-in-the-loop AI covers how to design review so it stays real.

Practical rules we would set

  • Nothing goes out unreviewed. An RFI reply can change scope, cost or liability. It leaves as a draft under a named reviewer, and the system has no way to send it alone.
  • Every answer shows document, sheet and revision. If it cannot cite, it says so.
  • Superseded documents stay marked. Keep them for the record, and keep them out of default answers.
  • Projects keep their walls. An answer for one owner’s job should not draw on another owner’s documents unless you have decided that is allowed.
  • Check the contract before uploading. Owner agreements and NDAs may limit where project documents can go. Our guide to AI security and data privacy covers what to ask a vendor.
  • Ask your broker. We found no carrier policy language on AI use, so we will not tell you how your professional liability coverage treats it. Get that answer in writing.

A sensible first project

Start small enough that a wrong answer is cheap, and test before anyone relies on it.

  1. Pick one live project with a defined current set, and one workflow. RFI screening is a good default.
  2. Record a baseline first: reply times from your log, plus a sample of how long searching really takes.
  3. Load the current set, mark superseded documents, and apply project permissions.
  4. Back-test on closed RFIs. Hide the real answers, run the questions, and have a licensed reviewer score the results, including whether the tool admits when something is missing.
  5. Run it live with drafts only and a named reviewer on each one.
  6. Decide against the baseline. If reviewers do not trust the drafts, or the numbers did not move, stop or change it.

That is the kind of work we do for architecture, engineering and construction firms. A senior scientist works on every project, your data stays in your accounts, and people approve anything that cannot be undone. The usual first step is a fixed-price, two-week AI Assessment, credited toward a pilot, which tells you whether a workflow is worth piloting at all. How to start with AI walks through the full sequence, and firms with an electrical or specialty trade side should also read AI for electrical contractors.

Questions

Can AI answer RFIs?

It can search the documents, flag duplicates and draft a cited reply. It should not send one. A reply can change scope, cost or liability, so a named reviewer checks the citations and sends it. We found no reliable figure for time saved at a small or midsize firm.

Can AI review submittals against the spec?

It can build the submittal log and line up product data against spec requirements, then draft comments for the engineer or architect. We found no reliable production accuracy data, so test it on past submittals with known outcomes. The stamp stays with a person.

Who is liable if AI gets a spec wrong?

We cannot give legal advice. As of November 2026, NCARB’s position is that the licensed practitioner remains in responsible control, which points to the firm and the professional, with AI treated as a tool.[7] Ask your attorney and your insurance broker how this applies to your contracts and coverage.

Is our project data safe in an AI tool?

That depends on the tool, the contract and the setup. Check owner agreements and NDAs before uploading, keep permissions by project, and find out where data is stored and whether it trains anyone’s models. We keep client data in the client’s own accounts.

Do we need clean data before we start?

For one project, you need a defined current set, clear revisions and sensible permissions. You do not need to clean your whole archive first.

Does this make sense for a firm under 50 people?

Sometimes. Reported adoption in architecture has been driven by firms of 50 or more, and the Dodge survey does not reach firms under $25M in revenue, so the evidence is thin.[4][5] A small firm with one person who knows where everything is may gain less from search than a firm with many live projects. The Assessment exists to answer this for your firm.

Will AI solve our staffing shortage?

No. It can take reading and drafting off estimators and project managers, who are hard to hire. It does not replace their judgment or the crews on site, and we found no reliable measure of how much capacity it frees up at a small firm.

Sources

  1. PlanGrid and FMI (vendor press release), New Research from PlanGrid and FMI Identifies Factors Costing the Construction Industry More Than $177 Billion Annually, August 2018.
  2. Navigant Construction Forum (Aconex data), Impact & Control of RFIs on Construction Projects, April 2013.
  3. Associated General Contractors of America, 2025 Workforce Survey Analysis, 2025.
  4. Dodge Construction Network with CMiC, AI for Contractors: Awareness, Use and Impact of Artificial Intelligence for Project and Company Management, SmartMarket Brief (third-party copy), Survey fielded September and October 2025.
  5. American Institute of Architects, New research explores perceptions and opportunities of artificial intelligence in architecture, March 11, 2025.
  6. Building Design + Construction, on the Deltek Clarity study, AI adoption surging across AE industry, May 19, 2025.
  7. Building Enclosure, NCARB’s Issues Statement on the Use of AI in Architecture, November 14, 2024.
  8. National Society of Professional Engineers, NSPE Position Statement No. 03-1774, Artificial Intelligence, Adopted September 2023 in the copy read.
A practical place to start